Indian Creek Seawall Project Not Compliant With Environmental Regs

Susan Askew
Susan Askew

Indian Creek Seawall Project Not Compliant With Environmental Regs:

contractor ordered to stop work

Miami Beach City Manager Jimmy Morales has notified Commissioners that the contractor installing the new seawall along Indian Creek is not in compliance with environmental policies and regulations. Morales wrote in a Letter to Commission that a review of the seawall replacement project identified areas of non-compliance that require corrective action.
 
Specifically, he wrote:
  1. Sections of the seawall have been completed prior to receiving verification from the U.S. Army Corps of Engineers.
  2. Sections of the seawall were installed beyond the allowed maximum distance from the wet face of the seawall.
  3. Spoil piles were staged adjacent to the Indian Creek waterway not consistent with sediment and erosion control Best Management Practices.
Morales stated, “I am troubled by these findings and the lack of adherence to environmental policies and regulations. I am therefore closely studying the operations and practices in the engineering division, as well as the contractual responsibilities of our environmental consultant, Stantec, and construction contractor, Shoreline Foundation.”
 
He said changes will be made to ensure such a situation does not happen again and noted two corrective actions that have already been taken. The contractor, Shoreline Foundation, has been put on notice of the issues and directed to stop all work on the project. In addition, the improperly installed spoil piles were removed within 48 hours of notice to the contractor.
 
“I am committed to bringing this project fully into compliance as quickly as possible and my team will be meeting again with the contractor and the regulatory agencies in the coming weeks to agree on an appropriate plan of action,” Morales wrote.
 
“Rest assured that my administration is committed to investing in replacing aging infrastructure and adapting to climate change while also complying with all environmental regulations that protect the beauty and value of our natural systems. I know that the two are not mutually exclusive,” he said.
 
The overall flood mitigation project area encompasses Indian Creek Drive between 25th and 41st Streets. It includes installation of a new storm water drainage system with a pump station at 32nd Street, upsizing sections of the existing storm water drainage system, elevating the roadway, and rebuilding the public seawall between 26th and 41st Streets. In the meantime, traffic detours are in place, making driving in the area painful. According to the project web page, the project was expected to be completed last fall.
 
Photos: City of Miami Beach
 

indian creek improvement project moves forward


Susan Askew
Susan Askew
road and greenway construction to begin later this year

Indian Creek Seawall Project Fallout


Susan Askew
Susan Askew
city engineer on administrative leave, timeline extended

another neighborhood asks questions about raising roads

La Gorce , Lakeview


Susan Askew
Susan Askew
lakeview residents hold grassroots meeting

Update on indian creek project's lack of permits

Resiliency


Susan Askew
Susan Askew
corrective actions will “very likely” include removing part of the new seawall